Associate a stakeholder with a work package
If you have not already done so by creating your work packages and sub-work packages, you can associate one or more stakeholders to your work packages.
By associating an stakeholder with a work package, this allows you to display the work package distribution table by stakeholder. This will allow you to assign a remark to the work package and the stakeholder. To assign a stakeholder to a work package:
Press the icon... ,
Then click on Link a participant,
Select the speaker and press OK.
![](https://storage.crisp.chat/users/helpdesk/website/6dbe8cfcdd8cb000/066982e0-d3e6-42ba-8544-73a809_1fpjsr0.png)
By associating an stakeholder with a work package, this allows you to display the work package distribution table by stakeholder. This will allow you to assign a remark to the work package and the stakeholder. To assign a stakeholder to a work package:
Press the icon... ,
Then click on Link a participant,
Select the speaker and press OK.